Top 10 Power Plant Of Bangladesh || ETechBD24


Top 10 Power Plant Of Bangladesh 


Top 10 Power Plant Of Bangladesh || ETechBD24

Top Most Powerful Power Plants of Bangladesh is :

1) Rooppur Nuclear Power Plant, Ishwardi ( 2400 MW)
2) Meghnaghat CCGF Power Plant, Meghnaghat (450MW )
3) Ashuganj stream power plant, Ashuganj (450 MW )
4) Raozan Gas Power Plant (420 MW)
5) Bheramara Combined Cycle Power Plant (410 MW)
6) Haripur Combined Cycle Power Plant (412 MW)
7) Ghorasal Power Plant unit 7 (365 MW)
8) Haripur CC Gas Power Plant (360 MW)
9) Summit Bibiyana Power Plant ( 341 MW)
10) Shajibazar Power Plant (330MW)

1) Rooppur Nuclear Power Plant, Ishwardi


Rooppur Nuclear Power Plant, Ishwardi || ETechBD24

PLANT TYPE: Nuclear power plant
LOCATION: Rooppur, Ishwardi, Pabna, Bangladesh
CAPACITY: 2.4GW / 2400 MW
CONSTRUCTION STARTED: 2017

Details: 

The Government of Bangladesh is building its first nuclear power plant in Rooppur on the east side of the river Padma near Ishwardi in the Pabna district of Bangladesh. The project is being implemented by the Bangladesh Atomic Energy Commission (BAEC), under the guidance of the Science and Technology Ministry of the Government of Bangladesh. The nuclear power plant (NPP) will include two units namely Rooppur Unit-1 and Rooppur Unit-2 with a capacity of 1.2GW each. Foundation stone for the Rooppur NPP was laid in October 2013 and the first concrete for the main construction phase was poured in November 2017. Rooppur Unit-1 is scheduled to commence operations in 2023, while Rooppur Unit-2 is due to come online in 2024. The project will provide low-cost electricity and create new jobs in Bangladesh. The power production in Bangladesh currently exceeds 4GW a year. The new plant will increase the country’s power production and enable it to achieve energy independence. 

Rooppur NPP construction details:

Construction of the nuclear power plant has been divided into stages, including the preparatory and main stages. The preparatory construction stage work was carried out during 2015-2016. It included the construction of amenities and office buildings, roads, security fences, and storage facilities.
The main construction works include excavation works, the pit water removal system, development of pit for units one and two, soil stabilization works, and foundations for both the reactor units.


2) Meghnaghat CCGF Power Plant, Meghnaghat


Meghnaghat CCGF Power Plant || ETechBD24


OUTPUT: 450MW
PLANT TYPE: Combined Cycle Gas Turbine (CCGT) 
LOCATION: Meghnaghat, Banglades
INVESTMENT: $289.6M

Details:

The Meghnaghat 450MW combined-cycle gas-fired power plant is on a 25.09ha site, 22km south of Dhaka on the northern bank of the Meghna River. The $289.6M plant was built by US-based AES (Allied Energy Systems) over a 22-year power purchase agreement with Bangladesh Power Development Board (BPDB). Operations at the plant began on November 2002. The Bangladeshi Government has been purchasing electricity from the Meghnaghat power plant at a price below two cents per unit, which is considered to be the lowest ever electricity price in the world. Pendekar Energy Group sought approval from the Power Ministry for enhancing the capacity of the Meghnaghat power plant by 170MW.  Named Meghnaghat I, the second phase, 335MW dual-fuel combined-cycle unit became operational in 2014.


3) Ashuganj stream power plant, Ashuganj

Ashuganj stream power plant || ETechBD24

PLANT TYPE: Combined Cycle Gas Turbine (CCGT)
LOCATION: Ashuganj, Dhaka, Bangladesh
CAPACITY: 450 MW

Details:

Combined Cycle (South) unit of Ashuganj Power Station Company has started producing 450 MW in Brahmanbaria. This is a gas-based power plant that will contribute reduce the deficit of electricity. This power plant has begun to produce electricity commercially from Sunday afternoon. The sources said this gas-based unit has been added to the national grid more 450 MW. This power plant is one of the largest units in the country's electricity power plants. This power plant reducing the deficit and will keep an important role in the national economy. According to the technical department of the plant funeral, Ashuganj Power Station Company owns around 10 acres of land. Now from 8 units of Ashuganj power station, 1,132 MW electricity is being produced. Under construction 450 Combined Circle (North) unit will be ready to produce electricity from 2017. The new unit is to produce a stream of almost one and a half thousand MW of electricity from the power plant which will be supplied to the national grid. Much of the country's electricity demand with the introduction of each unit will be resolved.

4) Raozan Gas Power Plant


Raozan Gas Power Plant || ETechBD24
                                  


Type: Gas Power Plant
Area: Chittagong
Kind of Fuel: Natural Gas
Origin of Fuel: Bakhrabad Gas System Limited
Power Capacity: 420 MW (2 x 210 MW)
Owner: Bangladesh Power Development Board (BPDB)
Shareholders: Government of Bangladesh
Activity since: 1993

Details:

The power station consists of two identical gas-fired units with an initial capacity of 210 MW and generating capacity of 180 MW both. It is supplied from the Bakhrabad and Feni gas fields, and from the Sangu offshore field. The N210-12.9-538/538 super high-pressure intermediate reheat condensing, three cylinders double exhaustion turbo set turbine, installed at Unit 1, was manufactured by Dong Fang of China. It has a rated capacity of 210 MW and a normal speed of 3,000 RPM. The steam flow at rated parameter at full load is 652.5 t/h at the temperature of 538 °C (1,000 °F) with a live steam pressure of 12.9 MPa. The turbine was delivered in July 1991.


5) Bheramara Combined Cycle Power Plant

Bheramara Combined Cycle Power Plant || ETechBD24

Type: Gas Power Plant 

Power Plant Location: Bahirchar, Bheramara, Kushtia.

Generation Capacity: 410 MW 

Fuel Type: Dual Fuel (Natural Gas + HSD)
Executive Agency: northwest Power Generation Company Limited (A representative of Bangladesh Power Development Board)

EPC Cost: 

USD: 178,788,328;
BDT: 2,562,922,636;
EUR: 8,510,300.

Total Project:

Cost GOB: BDT 91,939.59 Lac plus
PA: BDT 322,108.42 Lac
EPC Contract Signing Date: 16/03/2014
Manufacturer of GT and ST Mitsubishi Hitachi Power Systems (MHPS)
Commercial Operation Date: 09/05/2017 (Simple Cycle), 14/12/2017 (Combined Cycle)

6) Haripur Combined Cycle Power Plant


Haripur Power Plant || ETechBD24



Plant Location: Haripur, Bandar, Narayanganj
Total Capacity: 412 MW (Net) 
Fuel: Natural Gas
EPC Contract Signing: 09th Feb 2011
EPC Contract Effective: 14th Feb 2011
Commercial Operation Date(COD): 06th Apr 2014
EPC Contract Price: 349 Million USD
Financed By: Japan International Cooperation Agency (JICA) and GOB.
EPC Contractor: Marubeni Corporation, Japan.

Executive Agency: Electricity Generation Company of Bangladesh Ltd. 

Project Cost: 
EGCB Cost: 50.00 Lakh Taka
DPA Cost: 283,570.95 Lakh Taka
GOB Cost: 28,394.78 Lakh Taka
Total Cost: 312,015.73 Lakh Taka


7) Ghorasal Power Plant unit 7


Ghorasal Power Plant || ETechBD24

PLANT TYPE: Combined Cycle Gas Turbine (CCGT)
LOCATION: Ashuganj, Dhaka, Bangladesh
CAPACITY: 365 MW


Details:

300-450 MW GAS BASED COMBINED CYCLE POWER PLANT undertaken by NEPC passed a simple cycle for 168 hours trial run smoothly. Operating parameters, the economic and technical indexes all achieved their superiority and all the rate of putting automatics into operation was 100% in the duration of the trial run.

All people in the project department work together and coordinate closely with each other to overcome the high temperature, frequent rainfall, tight schedule, heavy tasks, equipment defects, and other difficulties since the contract was officially performed on August 16th, 2015. Eventually, the generating units went through the trial run for 168 hours on the schedule. The units are running stably at present and all people in the project department are an all-out sprint with working enthusiasm to achieve the combined cycle by the end of this year.

8) Haripur CC Gas Power Plant 

Haripur CC Gas Power Plant || ETechBD24

Type: Gas Power Plant
Area: Dhaka
Kind of Fuel: Natural Gas, Fuel Oil
Power Capacity: 360 MW (1 x 125 MW, 1 x 235 MW)
Owner: Haripur Power Limited (HPL)
Shareholders: Pendekar Energy Limited (PEL) (Powertek Ventures Ltd)
Activity since: 2001 


9) Summit Bibiyana Power Plant


Summit Bibiyana Power Plant || ETechBD24

Project Name: Bibiyana 341 MW Power Plant on Build, Own & Operate (BOO) basis
Type: Combined Cycle Gas Turbine
Technology: Heavy-duty 9FA gas turbine from General Electric USA
Fuel: Natural Gas
Installed Capacity: 352 MW
Address: Paul, Afrujganj, Nabiganj, Dist: Habiganj-3203, Bangladesh
Commercial Operation Date: Simple Cycle: 06 June 2015 | Combined Cycle: 28 December 2015

Details:

The water requirement of the project is met from the river Kushiyara. River water intake system supply water for the cooling system, an auxiliary cooling circuit as well as other power plant needs such as service and fire-fighting water. The water drainage system comprises a domestic sewage treatment system, industrial wastewater treatment system and stormwater drainage system. The wastewater is treated to meet applicable environmental guidelines.

10) Shajibazar Power Plant


Shajibazar Power Plant || ETechBD24
                             

PLANT TYPE: Combined Cycle Gas Turbine (CCGT)
LOCATION: Shajibazar,  Hobigonj, Bangladesh
CAPACITY: 330MW

Details:

A Combined Cycle Power Plant of a total of 330 MW +/- 20% capacity at site conditions (35°C, 1,013 bar, 98% R.H.) has been intended to be set up by Bangladesh Power Development Board at Shahjibazar, Hobigonj, Bangladesh. Approx. 25 acres of land is allocated for the implementation of this project. Natural Gas will be used as fuel for this Power Plant.

The Power Station step-up transformers have been connected with the 230 Kv Power Plant Sub-Station through underground cable and other necessary electrical equipment as shown in the straight-line diagram.

Tags:

bangladesh,ruppur nuclear power plant,top 10 mega project in bangladesh,power plant,top 10,top 5 mega project in bangladesh,bangladesh economy,rooppur power plant,power plant in bangladesh,top 10 project of bangladesh to change economy,power plants in bangladesh,power,bangladesh nuclear plant,top 10 garments in bangladesh.rmg in bangladesh,development of bangladesh,bangladesh power plant,bangladesh,ruppur nuclear power plant,nuclear power plant,bangladesh nuclear plant,power plant in bangladesh,payra power plant,ruppur power plant,rooppur nuclear power plant bangladesh,power,rooppur nuclear power plant in bangladesh,protected power of bangladesh,rooppur nuclear power plant,rooppur nuclear power plant project,bangladesh power development board,bangladesh power plant,india bangladesh power plant,nuclear power plant,rooppur nuclear power plant,payra power plant,power plant,power,power plant in bangladesh,ruppur nuclear power plant,rooppur nuclear power plant project,bangladesh nuclear plant,nuclear power,view in one blink of payra power plant,power plant clash,rampal power plant,ruppur power plant,kaptai power plant,rooppur power plant,russian power plant,power plant documentary,ruppur nuclear power plant,nuclear power plant,rooppur nuclear power plant,payra power plant,power plant,rooppur nuclear power plant project,bangladesh nuclear plant,ruppur power plant,payra 1320 mw power plant,payra power plant patuakhali,power,bangladesh nuclear power plant ruppur |,wind power plant,rampal power plant,kaptai power plant,#power plant list,rooppur power plant,power plant documentary

Post a Comment

0 Comments